Naples Condo Renovation Board Approval Checklist

Everything a Naples association expects with a renovation application, in the order it is usually asked for. Download it, or let us prepare the package at no charge.

Why boards say no

Most refusals we read about come down to three things: the insurance certificate names the wrong entity, the schedule falls outside the building's work window, or the drawings do not say clearly that exterior walls, windows, balconies and shared structure are untouched. The checklist below exists to close those gaps before the board meets.

Timing for the summer window

Most Naples buildings allow renovation from May to October. Boards usually meet monthly and want applications before their last spring meeting. Working back: book by March, design and selections in March and April, application in April, start in May. Owners who leave in April sign the contract before they go and the work runs while they are away.

The sixteen enclosures

  1. The association's own application form. Always first, always the building's version.
  2. Owner authorization. A signed line saying you authorize the work and the contractor.
  3. License copy and DBPR printout. CGC1534542 and the live state record.
  4. Insurance certificate. General liability naming the association's exact legal name as certificate holder.
  5. Workers' compensation certificate.
  6. Plain-English scope letter. What changes, and that exterior walls, windows, balcony and shared structure do not.
  7. Existing and proposed drawings.
  8. Product list and spec sheets. Especially flooring.
  9. Flooring and sound-control details. Underlayment rating where the building requires one.
  10. Engineering letter. If a wall or slab is touched.
  11. Work schedule. Inside the window, with noisy days marked.
  12. Building logistics plan. Elevator bookings and protection, parking, loading, debris route, common-area protection.
  13. Signed rules acknowledgment. The contractor has read the building rules.
  14. Emergency contacts and water shut-off plan.
  15. Fees and deposits. Who pays which, and when.
  16. The permit application or issued permit.

Two rules we keep: never promise approval or a date, and never describe the association as 'additional insured' without the insurer's endorsement. Florida condo law on alterations is Statute 718.113.

Download the checklist

A one-page PDF of the sixteen items with tick boxes. Download the checklist PDF

The download will ask for an email address so we can send updates when a building changes its rules. Unchecked by default, no texts without separate consent.

What the board package contains

Sent on top of every association application, with the building's own form first. Sixteen enclosures:

  1. Association application
  2. Owner authorization
  3. License copy and DBPR printout
  4. Insurance certificate naming the association's exact legal name
  5. Workers' compensation
  6. Plain-English scope letter: no changes to exterior walls, windows, balcony or shared structure
  7. Existing and proposed drawings
  8. Product list and spec sheets
  9. Flooring and sound-control details
  10. Engineering letter if required
  11. Work schedule inside the approved window, with noisy days marked
  12. Building logistics plan: elevator, parking, loading, debris route, common-area protection
  13. Signed rules acknowledgment
  14. Emergency contacts and water shut-off plan
  15. Fees and deposits
  16. The permit application or issued permit

We never promise approval or a date. The board decides. Florida condo law on alterations: Statute 718.113.

FAQ

Questions Naples owners ask

Do you prepare the board package?
Yes, at no charge, with the building's own form on top. Every item on this page is in it.
How early should I apply?
Before the board's last spring meeting, usually April, for a May start. Book with us by March.
Can the board refuse?
Yes, and we never promise approval. A complete package with the right insurance name and a schedule inside the window removes the usual reasons.

Not the cheapest. Never a surprise.

Tell us about the room. We'll send a price you can check.

A written, itemized estimate after the walkthrough, held for 30 days, with the payment schedule and warranty attached. No pressure visit, no lump sums.

Text a photo of your kitchen to (239) 000-0000We reply with a price range, not a sales call.

Step 1 of 4. What are you remodeling?

What are you remodeling?
Your property
Budget and timing

Budget

Timing

How to reach you

Next: your property, then budget and timing, then how to reach you. Nothing is shared and there is no obligation.